On the M-12 motorway Stryi – Ternopil – Kropyvnytskyi – Znamianka, on the section from Ternopil to the border of the Khmelnytskyi region, routine and medium repairs are underway.
As of May 31, 2018, the following has already been completed:
milling of the road surface – 29.7
km;
regeneration of the base using
cold recycling technology – 27 km;
lower layer of asphalt concrete – 20.7 km;
upper layer of asphalt concrete 2.3 km;
widening of the carriageway – 0.96 km.
Repair work is being carried out simultaneously on several sections.